d02 - Mounting and installation SE02-D1

Introduction

The basic construction and the materials for construction are described in guideline b2. This guideline shows the practical aspects and experience from the installation.

 

Components description

Anchor rod M8x110
Role: anchoring the bracket to the wall.

Characteristics:

Drill bit diameter 10 mm
Anchor size M8
Anchor length 110 mm
Material composition Steel 8.8
Environmental conditions Outdoor, Underwater, fresh water
Approvals / test reports ETA, Fire
PROFIS software Yes

 

Injectable mortar HIT-HY 270 330/2

Role: Adhesive anchoring system for anchor fastenings in hollow and solid masonry

Characteristics:

Base materials Concrete (aerated), Masonry (hollow), Masonry (solid), Some types of natural stone
Base material condition Dry, Wet
Cleaning procedures Compressed-air cleaning, Manual cleaning
Anchoring elements HIT-IC internally-threaded rods, HIT-SC mesh sleeves, HIT-S mesh sleeves, HIT-V threaded rods
Approvals / test reports ETA, Fire
Environmental conditions Indoor, damp conditions, Indoor, dry conditions, Indoor, ventilated facades, Outdoor
Mixer types HIT-RE-M
In-service temperature -40 – 80 °C
Installation tools HDM, HDE 500-A22

Mesh sleeve HIT-SC 16×85
Role:

Characteristics:

Drill bit diameter 16 mm
Anchor size 8/10 mm
Anchor length 85 mm
Material composition Plastic
Environmental conditions Indoor, damp conditions, Indoor, dry conditions, Indoor, ventilated facades, Outdoor, Underwater, fresh water

 

Framework Installation

Wall conditions:
The wall must be even and free of obstacles, such as gutters, thick cable tubes or external pillars that would disrupt its flatness. In opposite case, please see remark 1 below.
The drill holes on the wall must be done with the use of a multi-line laser.

 

Installation of simple canopy

  • Assemble the sheet part SE02-D1-S-1 above the canopy using DIN7981-D3.5X13A2.
  • Assemble the sub-assemblies SE02-D1-S-2 using M8 hexagon nuts and serrated lock washers.
  • Make holes in the wall according to the following drawing and attach the structure to the wall using anchor rods.
  • Adjust the angle turning the threaded rods ” Detail A”.

Overview of the canopy framework.

Drawing of holes on the wall 

Anchor rods for sub-assemblies and anchor rods for canopy (red circle).

 

Installation of double canopy

  • Assemble the sheet parts SE02-D1-S-1 above the canopy using DIN7981-D3.5X13A2.
  • Assemble the sub-assemblies SE02-D1-S-2 using M8 hexagon nuts and serrated lock washers.
  • Make holes in the wall according to the following drawing and attach the structure to the wall using anchor bolts.
  • Adjust the angle turning the threaded rods “Detail A”.

 

Anchor rods for sub-assemblies Anchor rods for canopy and top view

Tools

  • Electricity Generator
  • Electric cutter
  • Mechanical level
  • Screwdrivers
  • Wrench
  • Rule
  • Crane or Scaffolding

Safety equipment

  • Protection glasses
  • Safety shoes
  • Gloves
  • Safety helmet
  • Safety belt

 

Text written by HERON, Greece